Project Timeframe: Construction is set to begin February 6, 2017 and to conclude July 6, 2017.

Project Location: Construction will be in 5th Street Right-of-Way from NM 118 (Hwy "66") to Park Avenue, and in Park Avenue Right-of-Way from 6th Street to 3rd Street. 5th Street South bound lane will remain open from NM 118 (Hwy "66") to West Morgan Avenue to maintain access to businesses and residences. Parking along 5th Street will not be allowed during construction to allow for vehicle traffic access.

Project Schedule: Construction will Start at the intersection of 5th Street and NM 118 (Hwy "66") and continue South along 5th Street as construction progresses. 


             Phase I: 5th Street Right-of-Way from NM 118 (Hwy "66") to West Mesa Avenue.
             Phase II: 5th Street Right-of-Way from West Mesa Avenue to Park Avenue.
             Phase Ill: Park Avenue Right-of-Way from 3rd Street to 6th Street.

Contractor will make every effort to inform public and to maximize access to businesses and residences.

Project Hours: Construction work is scheduled between the hours of 7:00 AM - 5:30 PM Sunday through Saturday.

Attached: Project Traffic Control Plan.